INFRASTRUCTURE IMPROVEMENTS ARE MOVING ALONG WELL IN SUNSET STATION
It’s exciting to see Sunset Station coming together to be the lifestyle community we envisioned! We have made great progress on the recreational amenity area and the network of trails that will be within the community.
Our playground equipment will soon be installed, and our network of trails is under construction. We are also moving soil and surface grading in preparation for the common
area onsite sidewalks.
Construction of the new sidewalk along Sunset Hills Road linking American Dream Way to Old Reston Avenue is underway. Included
in this work are American Dream Way at Sunset Hills Road intersection improvements adding new pedestrian crossing signals as well as a dedicated bike lane.
SUNSET STATION UPDATE
Sunset Station opened it’s first building to VIPs in mid-August and there have been two sales so far. The furnished model will be
open for tours in November.
If you would like more information about Sunset Station or to sign up for their buyer interest list, please visit
https://dreamfindershomes.com/new-homes/va/reston/sunset-station/

- AMERICAN DREAM WAY PHASE 2 -
THE DEMOLITION OF THE FNMA BUILDING HAS BEGUN!
The preconstruction meeting with Fairfax County was completed on September 5th, and we have begun the demolition of the FNMA building! We are excited to begin this process to prepare the site for future use. As we communicated last month,
throughout the demolition, the pedestrian gate will be closed for safety and will not reopen until we can assure it is safe.
As part of our preparations, we have installed vibration monitoring equipment, and all visual inspections of applicable neighboring homes by ECS have been completed. Demolition work is expected to occur between Monday – Friday, between the hours of 8 am and 4 pm. If you have any questions about the demolition project, please contact our Hotline at 703-423-0995.
We will keep everyone informed through this newsletter, on our social media accounts, and through direct emails. Thank you for your understanding and cooperation as we move forward with this project!