UPDATE ON THE FNMA OFFICE BUILDING GARAGE DEMOLITION

The demolition of the garage structure is going well, and we expect the majority of the work to be complete by the end of May 2026. Once the garage has been successfully demolished, efforts will transition to backfilling in the void left by the building and garage removal.


The garage demolition uses heavy equipment to demolish uses heavy equipment to demolish the structural columns and robust concrete slabs within the structure. Given that the parking structure is partially underground, the demolition work may sound different relative to demolition of the office building.


The Concrete Processing/Recycling process is ongoing, with the specialized

recycling equipment operating daily. This machine creates usable material to backfill the voids left by the office building and garage footprints. The balance 

of demolished materials that cannot be used will be properly removed by truck via the southeast entrance to Sunset Hills Road.  


If you have any questions about the FNMA office building garage demolition or the ongoing work at the site, please contact us at the Hotline phone number listed in the newsletter below.


CELEBRATE SPRING IN SUNSET STATION’S NEW PLAYGROUND


We are excited to announce that the new playground in Sunset Station has been completed and is ready for fun play dates! The playground features high-quality playground equipment designed to provide a fun and safe experience for younger children. We would

love to feature photos of your children enjoying the playground. Please send those to info@americandreamwayproject.com.


New Paragraph

SUNSET STATION UPDATE


Sunset Station has welcomed its first new residents into the community! The residents have shared that everyone has been super friendly and they are looking forward to getting to know their neighbors!


Sunset Stations has sold 15 townhomes and its one condominiumbuilding sold out within three weeks. Dream Finders Homes has just

opened two new buildings for future homes to be delivered in the next few months.




By Regina Marston March 23, 2026
THE FNMA OFFICE BUILDING DEMOLITION Reaches Major Milestone
By Regina Marston February 18, 2026
THE FNMA OFFICE BUILDING DEMOLITION IS COMPLETE
By Regina Marston January 20, 2026
THE FNMA BUILDING EXPECTED TO BE LEVELED BY LATE FEBRUARY 2026
By Regina Marston December 18, 2025
WE’RE CELEBRATING THE HOLIDAYS with Donations to Coats for Kids!
By Regina Marston November 26, 2025
- AMERICAN DREAM WAY PHASE 1 - WE’RE MAKING GREAT PROGRESS ON SUNSET STATION
By Regina Marston October 24, 2025
- AMERICAN DREAM WAY PHASE 1 - INFRASTRUCTURE IMPROVEMENTS ARE MOVING ALONG WELL IN SUNSET STATION
By Regina Marston September 22, 2025
- AMERICAN DREAM WAY PHASE 1 - INFRASTRUCTURE IMPROVEMENTS ARE MOVING ALONG WELL IN SUNSET STATION
By Regina Marston August 15, 2025
- AMERICAN DREAM WAY PHASE 1 - CONSTRUCTION ON SUNSET STATION AMENITIES AND TRAILS HAS StARTED!
By Regina Marston July 22, 2025
- AMERICAN DREAM WAY PHASE 1 - Major Improvements on Sunset Station Taking Place This Summer!
By Regina Marston June 19, 2025
- AMERICAN DREAM WAY PHASE 1 - SUMMER SIZZLES IN THE AMERICAN DREAM WAY PROJECT!